Patented Z-section sheet piles were extruded using the Bio Composites Pilot Line at the Advanced Structures and Composites Center.
Extruded Sheet Piles
600 lineal feet of pile was extruded for the Witter Farm demostration project.
Trenches
Trenches were dug and filled with gravel before sheet piles were installed.
Cutting Anchors
6" x 6" wooden beam anchors for the sheet piles being cut, then attached to the concrete wall to stabilize the cantilevered retaining wall system.
Loading Materials
Material being loaded at the Center to transport to Witter Farm.
Initial Instrumentation Installation
Instrumentation started in the pvc piping was installed and attached to a computer on site to collect data.
Sheet Pile Installation
Placing the third sheet pile by hand, the sheet pile placement took two days.
Tie-Back Supports
The wall is a tied-back design, that incorporates three 1,500lb concrete blocks attached to the wall using rebar and a steel plate. Here the concrete blocks are being placed.
Cap Installation
Caps being placed on the retaining wall.
Installed Cap
Cap on the smaller retaining wall once placed.
Wall Support Complete
Rebar being tied down to a steel plate completing the larger of the two retaining walls.
Instrumentation Installation
Instrumentation installation was completed by Shane Bourgault, an Advanced Structures and Composites Center graduate student. Strain data of the piles and soil temperature will be monitored over a one-year period.